The brick on the rear of our home is now 100% done, including the back porch area.
![]() They nearly finished the south side today too - all except for a very small portion on the southeast corner.
![]() Progress at the end of Day 11 of brickwork.
![]() August 24, 2004
Compared to at the end of Day 12.
![]() August 27, 2004
Drywall (hanging) is moving right along - this being one of our upstairs bedrooms.
![]() And this the office in the basement (looks quite a bit brighter than previous photo because the camera's flash activated on this one).
![]() Only the front remains to be bricked.
![]() They are also working on a small retaining wall which extends near the northeast corner of the home.
![]() August 30, 2004
The next stage of completing the dry wall work is the "finishing" portion, initially this includes some taping.
![]() The east end of Bonus Room #2 after taping (you can see the pull-down attic stairs at the top right part of the photo - the attic is the 4th level of our home).
![]() Progress on both the retaining wall and the bay window area.
![]() |
||